17 Aug
[Elecktra arrives on
PI list Will help as
available]
Bob & Duncan go to
Gerlach to pick up
previously staged
wood (1-2 trips near
Gerlach) & deliver
to site.
|
18 Aug
Jim Crowley (Warrior)
arrives
Bob & Duncan begin
building back side
of letters
|
19 Aug
Bob, Duncan & Warrior
finish back, begin
building front side
of letters
|
20 Aug
Marcel Marcinkowski
Arrives
Kevin D. Hall
Arrives
Larry Breed arrives.
Bob, Duncan & Warrior
finish front side
of letters
|
21 Aug
David McParland Arrives
All hands lift and begin
attaching front to back
with 2x4s & plywood
|
22 Aug
Cary McHugh (Burning
Silicon list) Arrives
Bob, Duncan, Marcel,
Kevin & Larry finish
attaching front to
back with 2x4s & ply
David McP & Dea Nelson
(Dea on Playa Info
early list) working
on attaching cloth
Begin adding Facade
plywood
|
23 Aug
David McP & Dea Nelson
working on attaching cloth
Team finishes adding
Facade ply Late in day
(?if calm?)-lift/standup
piece onto burn platform
& rig.
Ember & Cary working on
rigging & burn platform.
|
24 Aug
Early Morning when air
still(?)-lift/standup
piece onto burn
platform & rig.
Rig flags and
lighting, test
in wind(?)
Ember working on
rigging.
|
25 Aug
OPENING BELL!!!
UP AND READY
|
26 Aug
|
27 Aug
|
28 Aug
|
29 Aug
|
30 Aug
THE
END
burns @ midnight
|